A measurement assumptions log is a dated record of every point where you measured, priced or described work on the basis of something the drawings and specification did not fully state. Each entry gives the assumption, where it came from, who confirmed it and what happens if it proves wrong. Kept alongside the take-off and issued with the quantities, it lets a reviewer, a client or a contractor see exactly what your Bill of Quantities (BoQ) rests on.
This guide is for quantity surveyors, small builders and architects who produce or check take-offs in UK practice. It covers what the log should contain, worked examples, how it links to NRM2 provisional quantities and sums, and how to keep it alive when drawings change.
TL;DR
- A measurement assumptions log records every assumption, allowance and unresolved query behind a set of quantities, so the BoQ can be reviewed and defended.
- Each entry needs a unique ID, the take-off item it affects, the assumption, its source, an owner, a status and a date.
- Where NRM2 cannot be applied because information is missing, the item becomes a provisional quantity or a provisional sum, and the log explains why.
- Update the log whenever a drawing revision, RFI response or instruction changes the basis, and keep the original entry for change documentation.
- Link every take-off line to its log entry by ID, so nobody has to hunt for the reasoning.
Table of Contents
- What a measurement assumptions log is
- Why NRM2 makes the log worth keeping
- What each entry should record
- Examples of measurement assumptions
- Assumption, provisional quantity or provisional sum?
- Setting up the log step by step
- Recording classifications and their cost implications
- Keeping the log current as drawings change
- When an assumption proves wrong
- Common mistakes
- Where drafting tools fit
- Where QuantiFlow fits
- FAQ
- Sources
What a measurement assumptions log is
Most search results for this phrase describe the project management version: a register of assumptions about budget, resources or timing that are tracked and turned into risks if they prove false. The measurement version has the same discipline but a narrower job. It sits with the take-off and records the judgement calls made while turning drawn information into quantities.
Measurement, in the words of the Designing Buildings wiki, turns drawn information into descriptions and quantities used to value, cost and price construction work, and taking off collates the measurable work into an unpriced bill of quantities. That conversion only works as far as the information allows. Where a dimension is missing, two drawings disagree or a specification is silent, you have to do one of three things: stop, ask, or assume and say so. The log is where "assume and say so" lives.
It is not a substitute for the BoQ preamble or for clarifications to the tenderer. It is the working record from which those documents are drawn, and it protects you when someone asks, three months later, why a quantity is what it is.
Why NRM2 makes the log worth keeping
The RICS New Rules of Measurement are the profession's standard measurement rules, and NRM2 covers detailed measurement for building works. The NRM2 text (October 2021 edition, effective 1 December 2021) is clear that the accuracy of a bill of quantities depends on the quality of information supplied by the client, designers and other project participants. Where that information is limited, the quantity surveyor or cost manager is expected to seek decisions on how the uncertainty should be managed.
That is the log's purpose in one sentence. It records the uncertainty, who was asked to decide, and what you did in the meantime.
The same document sets out the drawn information NRM2 expects: enough to describe the building assembly and temporary works, including general-arrangement, component and schematic drawings and, for refurbishment or demolition, record drawings. If what you were given falls short of that, the shortfall belongs in the log.
What each entry should record
A log that is too thin is useless and one that is too heavy is not maintained. The fields below are enough for most SME projects.
| Field | What to put in it | Why it matters |
|---|---|---|
| ID | A short unique reference, such as MA-014 | Lets a take-off line point to its reasoning |
| Take-off item | The BoQ or work section reference affected | Shows where the assumption bites |
| Drawing and revision | Drawing number and revision letter used | Ties the assumption to a dated basis |
| Assumption | The specific thing assumed, in one plain sentence | Makes it testable |
| Type | Assumption, allowance, provisional quantity, provisional sum or risk | Shows how it is carried in the BoQ |
| Source | Drawing note, specification clause, conversation, standard detail | Shows it was not invented |
| Confirmed by | Name and role of whoever agreed it | Gives accountability |
| Query status | Not raised, RFI issued, answered, closed | Shows whether it is still live |
| Impact | Quantity or value affected, if known | Prioritises what to chase |
| Date and revision of entry | When logged and when last changed | Preserves the audit trail |
Two further pieces of information are easy to forget. The first is the calculation basis. The NRM2 reissue of October 2022 is the sort of document that makes you think about what each figure means: whether it is the installed quantity, a purchase allowance or a pricing input are three different things, and the log should say which you are carrying. The second is the convention you used: units, rounding, boundary lines between elements, and what is included and excluded.
On rounding, NRM2 measures work net as fixed in position unless stated otherwise, measures dimensions to the nearest 10 mm, and generally states quantities to the nearest whole number, except tonnes, which are stated to two decimal places (RICS NRM2, October 2022 reissue). If you depart from any of this, for instance carrying a gross area for a quick budget bill, write the departure down.
Examples of measurement assumptions
Generic examples help less than ones you would recognise from a real set of drawings. These are typical situations on a small UK job, shown as log entries.
Missing dimension. The drainage layout shows an inspection chamber but no invert levels or depth. Log: "Chamber depth assumed 1.2 m for excavation and backfill measurement; no depth on drawing. Source: typical depth from adjacent run. Query raised with engineer. Status: open."

Drawing conflict. The ground-floor plan shows a 100 mm blockwork partition, the section shows 140 mm. Log: "Partition thickness taken from plan (100 mm). Conflict with section recorded. RFI issued to architect." The guide on drawing discrepancies goes through how to find, record and resolve this kind of conflict in more detail.
Range or unspecified rate basis. A specification gives a range for a finish allowance. Log: "Midpoint of the specified range used for pricing; to be replaced when selection is made."
Pending query. A cladding panel length is not dimensioned and waits on a manufacturer's detail. Log: "Panel length scaled from elevation pending query; quantity subject to change."
Scope of testing and commissioning. The specification mentions testing without stating extent. Log: "Testing scope assumed as one set of pressure tests per system; confirm with design team."
Existing conditions. On a refurbishment, record drawings show a wall position that has not been verified on site. Log: "Existing wall lengths taken from record drawing rev B; not surveyed."
Notice what these have in common: each is specific, each names a source or lack of one, and each says what happens next.
Assumption, provisional quantity or provisional sum?
Not every gap should stay an informal assumption. NRM2 gives defined routes, and the log should record which route each item takes.
A provisional quantity is, per NRM2, an estimated quantity of work that cannot be accurately determined at tender stage. Use it where the work is described but its extent is not known, such as rock excavation or the amount of made-up ground.
A provisional sum is different. The October 2022 update to NRM2 requires building components that cannot be measured and described under the tabulated rules to be treated as provisional sums and identified as either defined or undefined work. For a defined provisional sum, the rules require the following to be stated:
- the nature and construction of the work;
- its fixing location and interfaces;
- quantities indicating scope and extent;
- any specific limitations.
The log is the natural place to gather those four points before they go into the bill. If you cannot fill them in, that tells you the sum is undefined, and the contractor should be told so.
A simple rule for the log: if you can describe it and only the quantity is uncertain, it is an assumption or a provisional quantity. If you cannot measure or describe it, it is a provisional sum. If it is a possibility that may never occur, it is a risk and belongs in the risk register, cross-referenced by ID.
Setting up the log step by step
- Create it before you start measuring. Open the log when you open the take-off file, not after the first query. Entries written from memory a week later lose their sources.
- Record the information basis. List each drawing and specification document used, with revision and issue date. Every later entry refers back to this list.
- Log as you go. The moment you scale a dimension, apply a typical detail or skip a conflicting note, write the entry. One line is enough at this stage.
- Assign an ID and link it. Put the entry ID in the take-off line it affects. A reviewer reading the quantities should be able to jump to the reasoning without asking you.
- Classify each entry. Decide whether it is an assumption, allowance, provisional quantity, provisional sum or risk, and carry it that way into the BoQ.
- Raise the queries. Group open items into one RFI schedule per recipient. Fifteen separate emails get lost; one numbered list does not.
- Record who confirmed what. An assumption confirmed by the architect by email is stronger than one you made alone. Note the date and the person.
- Review before issue. Read the log as the person receiving the BoQ would. Anything unclear is a future dispute.
The same traceability idea applies at project scale. The article on linking each BoQ line to its drawing revision shows how revision references keep a take-off defensible when drawings move on.
Recording classifications and their cost implications
An assumption is rarely just a quantity question. Choosing between a provisional quantity and a provisional sum, or between an installed quantity and a purchase allowance, changes what the contractor prices and who carries the risk. Add an "estimating implication" note to entries with real money behind them: for example, that a material is carried as an allowance including waste, or that a quantity is net and waste is added in pricing. If you track material costs against the estimate as work proceeds, an approach such as tracking construction material costs in real time depends on knowing which basis each original quantity used, and the log supplies that.
Keeping the log current as drawings change
A log written once and filed is a snapshot. Drawings move, and the log must move with them.
- On every new drawing revision, check each open entry against the change. Entries may close, become wrong, or need re-pricing.
- When an RFI is answered, update the status, record the answer and its source, and change the take-off line if the quantity changes.
- When an assumption changes, do not overwrite the old text. Mark the old entry superseded, add the new one and cross-refer. The original basis is what you rely on if the change becomes a variation.
- Date every change. The log should show what you assumed on the day the bill was issued, not what you know now.
This approach is consistent with the NRM2 principle that quality of information drives quality of quantities: when information improves, the quantities should be re-examined and the record updated, with the original pricing basis kept.
Where a model is the source, the same rule holds. Quantities extracted from BIM carry assumptions of their own about element classification and modelling completeness, and the guides on BIM quantity extraction and BIM quantities verification cover what to check and record.
When an assumption proves wrong
It will happen. The chamber is 2.1 m deep, not 1.2 m. What matters is how quickly you can show the effect.
- Find the entry by its ID and the take-off lines that cite it.
- Record the new information, its source and the date.
- Recalculate the affected quantities and note the revised quantity and the difference.
- Mark the original entry superseded rather than deleting it.
- Tell whoever relies on the bill, in the form your contract requires.
Because the log shows the original basis, the discussion becomes about a documented change in information rather than about who made a mistake. That is a far easier conversation with a client or main contractor.
Common mistakes
- Vague wording. "Allowed for ground conditions" tells nobody anything. State depth, volume, rate basis.
- No source. An assumption without a source looks like a guess, even when it was a reasonable judgement.
- No owner. Every open item needs a named person responsible for closing it.
- Logs kept in email. Reasoning spread over inboxes cannot be audited. Keep one controlled document.
- Treating the log as a defence file only. Its best use is prompting the right questions early, while the design team can still answer cheaply.
- Deleting resolved entries. Close them, do not remove them.
Where drafting tools fit
Whatever tool produces your quantities, a draft is a draft. The article on why UK QSs must audit every automated draft makes the point that the judgement calls, and so the assumptions, remain yours. For a typical small project, the house extension take-off checks show where assumptions tend to cluster: foundations, existing structure interfaces and finishes allowances. The wider role of drawings in quantity measurement explains why drawing quality sets the ceiling on measurement quality.
Where QuantiFlow fits
QuantiFlow is in development. It reads construction drawings and produces a draft Bill of Quantities for a quantity surveyor to review and sign off, which is the stage where an assumptions log does its work.
If you want to follow its progress, you can find out more on the QuantiFlow site.
FAQ
What is the difference between an assumptions log and a risk register?
An assumptions log records what you took to be true in order to measure or price. A risk register records events that might happen and their consequences. An assumption that turns out to be doubtful can become a risk, so cross-reference the two by ID rather than duplicating text.
Do I need a measurement assumptions log on a small job?
Yes, though it can be short. Even a house extension has missing dimensions, drawing conflicts and allowances. A one-page log with ID, assumption, source, owner and status is enough, and it costs far less than reconstructing your reasoning after a dispute.
Should the log be issued with the Bill of Quantities?
The NRM2 approach is that where information is incomplete, the assumptions made should be stated rather than hidden. What you issue depends on the contract and the client. Issue the assumptions that affect pricing or scope, and keep the internal working notes, such as the full source trail, on file.
What should I do with assumptions I cannot confirm before tender?
Carry them as clearly worded provisional quantities or, where the work cannot be measured and described, as defined or undefined provisional sums, as NRM2 requires. Keep the entry open, record who you asked, and update it when an answer arrives.
Can I use a standard template?
Yes. Project management templates for assumption logs are a reasonable starting point, but add measurement-specific fields: take-off item reference, drawing revision, calculation basis and how the item is carried in the bill.
Sources
- RICS NRM: New Rules of Measurement
- RICS NRM2, October 2021 edition
- RICS NRM2, October 2022 reissue
- RICS NRM2, October 2022 update
- Measurement, Designing Buildings
- Construction material cost tracking, INGENIA
Recommended
- UK QSs: Stop NRM2 Measurement Mistakes With Practical QA Steps
- Construction measurement quality control: the UK SME guide
- Audit log best practices for UK quantity surveyors
- Measuring Variations for UK QSs: NRM2 From Instruction to Record
This article is for general information only and is not professional, legal or commercial advice. Quantity surveying decisions should be taken by a qualified professional with reference to the specific project, drawings and contract in question. Content is produced with AI assistance and reviewed before publication. QuantiFlow Ltd accepts no liability for reliance on it.