← Back to blog

Fire Stopping Takeoff: A Method for UK Quantity Surveyors

November 22, 2026
Fire Stopping Takeoff: A Method for UK Quantity Surveyors

Fire stopping is easy to under-measure because it rarely appears as a single drawn element. It sits in the gaps between other trades: the cable tray through a compartment wall, the pipe sleeve in a floor slab, the head-of-wall junction under a deck. A sound fire stopping takeoff starts from the fire strategy, builds a penetration schedule, and measures each item by the unit the tested system requires. This guide sets out that routine for UK quantity surveyors, small builders and architects, and where it most often goes wrong.

Quantiflow
Turn Drawings Into Measured Takeoffs
QuantiFlow uses AI to create structured, NRM2-aligned takeoffs from architectural drawings while leaving professional judgement with the quantity surveyor.
Visit

TL;DR

  • Start from the fire strategy and compartmentation drawings, not from every visible gap. Only openings in fire-resisting walls and floors need fire stopping.
  • Build a penetration schedule first: one tagged line per opening, with the element it passes through, the service, the size and the required fire resistance.
  • Count openings, not pipes. Separate new penetrations from existing ones, and record the system reference rather than a generic "fire sealant" description.
  • Allow for spacing and tested-detail constraints, which affect how many seals a layout can accommodate.
  • Keep the schedule traceable to drawing references so a reviewer or contractor can check any quantity in minutes.

Table of Contents

What fire stopping covers in a takeoff

Fire stopping means sealing openings, joints and gaps in fire-resisting walls and floors so that the element keeps its fire resistance. Midsummer Fire Protection's overview lists the places it is typically needed: cable trays and bundles, pipe penetrations, ventilation and extract ducts, damper interfaces, trunking and conduit, risers and shafts, movement joints, wall-to-floor and wall-to-soffit junctions, structural members, doorsets, refurbishment voids and openings left after services are removed.

For measurement, it helps to sort those into three families, because each is counted differently:

  1. Service penetrations: a pipe, duct, cable tray or conduit passing through a rated wall or floor. Measured as numbered items.
  2. Linear joints: movement joints, head-of-wall, wall-to-floor and perimeter gaps. Measured by length.
  3. Areas and voids: ceiling or roof-void cavity barriers and similar. Measured by area where the bill requires it.

The unit you finally use should follow the measurement rules and preliminaries of the bill you are producing. Whatever the unit, the item description should state the element being sealed, the fire resistance period and the system or product reference, so the price is for a defined, tested solution.

Why the fire strategy comes first

The most common source of both missed and padded quantities is treating the whole building as if it needed sealing. Midsummer Fire Protection advises establishing the need from the fire strategy and the compartmentation drawings, working out which walls and floors form fire-resisting boundaries, rather than reacting to every gap you see on a section.

In practice, that means collecting these before measuring anything:

  • The fire strategy report, or the fire-safety information on the architect's compartmentation plans.
  • Floor plans marked with compartment walls, protected shafts, protected lobbies and stair enclosures.
  • The specification section for fire stopping and any named manufacturers' tested systems.
  • Services drawings (mechanical, electrical, plumbing) to see what crosses those boundaries.

The point of timing matters for architects and builders too. Rockwool's fire-stopping standard details guide encourages early engagement on design, referring to ASFP Advisory Note 33 on designing passive fire protection. If the drawings you are measuring from are early-stage and the fire stopping is not yet detailed, that is a reason to carry a clearly worded provisional allowance, not a reason to leave the item out.

The rules that make fire stopping a measured item

You do not need to quote regulation to measure fire stopping, but you do need to know why the item exists and why a tested system, not a tube of mastic, is what you are pricing.

  • Approved Document B (England). Fire-stopping provisions, as summarised in the Midsummer guide above, require joints between fire-separating elements to be fire-stopped, and openings for pipes, ducts, conduits and cables to be kept as few and as small as practicable and fire-stopped. Proprietary tested systems may be used, and different materials suit different applications.
  • The 2025 amendments. The amendments to Approved Document B took effect in England on 2 March 2025. They include provision for an as-built plan showing fire-resisting construction and fire-separating elements, supplied to the dutyholder under Regulation 38. A clean penetration schedule is a useful starting point for that record. Scotland, Wales and Northern Ireland have their own building regulations, so check the relevant document for the project location.
  • Construction-phase risk. HSE's HSG168, Fire safety in construction, names fire and smoke spreading through a building because service openings through compartmentation have no fire stopping among the scenarios a construction-phase fire risk assessment must consider.
  • Temporary fire stopping. The FPA and UK Joint Code of Practice on fire prevention on construction sites (10th edition) calls for horizontal compartmentation at intervals not exceeding five floors, using temporary fire-stopping materials with at least 60 minutes' fire resistance until permanent fire stopping is installed, and for risers, shafts and ducts to be closed off with 30-minute self-closing doors at all levels. On taller or phased jobs, check whether the preliminaries need to carry this temporary work.

Step 1: Build the penetration schedule

A penetration schedule is the backbone of the takeoff. Walk each floor plan in turn and tag every sleeve, tray, duct and pipe that crosses a rated assembly. For each tag, record:

FieldWhat to recordWhy it matters
Tag numberUnique reference matching a drawing bubble or grid locationLets a reviewer trace the quantity to a sheet
ElementWall or floor type and its required fire resistanceThe seal must match the element it penetrates
ServicePipe, duct, tray, conduit or bundleDrives the choice of system
Material and sizeFor example, plastic pipe diameter, or tray widthTested systems are specific to the penetrating item
Opening sizeAperture dimensions if shownSets the seal size and product quantity
System referenceThe specified tested systemGoes on the bill item instead of a generic description
StatusNew, existing or removed serviceStops new and existing work being mixed

This tag-to-bubble approach is common practice in firestopping takeoff guidance. The principle is that every quantity can be traced back to a sheet. It also makes later revisions manageable, because a changed drawing affects identifiable rows rather than a lump sum.

Step 2: Read the right drawings

Different parts of the takeoff come from different sheets:

  • Compartment walls and floors come from the architect's plans and the fire strategy drawings.
  • Service crossings come from the services drawings, overlaid on those boundaries.
  • Linear joints and head-of-wall come from partition layouts and building sections. Services drawings will not show them.
  • Structural members passing through compartment lines come from the structural drawings.
  • Doorsets and their frames come from the door schedule. If you are measuring those anyway, the method in our five-step NRM2 door takeoff keeps the schedule consistent with the fire stopping around the frames.

On heating and hot-water packages, pipework to terminal units brings more crossings than the unit count suggests. If the specification calls for low surface temperature radiators, for example, mark where the connecting pipes pass through rated walls and floors in the schedule, so those openings are carried against the right system.

For wider services measurement, the NRM2 MEP takeoff steps show how to keep services quantities audit-ready, which feeds directly into your crossing count.

Step 3: Specify the system, not just the sealant

Fire-stopping products are tested for a specific type of penetration. Rockwool's guide notes that they are tested to the penetration type and that joints or valves should not be allowed to fall in line with the fire-stopping solution (ASFP Advisory Note 28). Practical consequences for the takeoff:

  • A seal for a steel pipe through a masonry wall is not automatically valid for a plastic pipe through plasterboard.
  • The system reference belongs in the item description, so the price reflects the actual tested solution.
  • If a drawing does not state the system, carry a provisional item that names the assumed system and the element it covers, and raise a query.

UL Solutions, in its guide to firestopping, lists what a good design considers: whether the seal is load-bearing or subject to movement, the required fire resistance period, insulation and water penetration requirements, the size of the service opening, and compatibility between the service and the system. Those are exactly the attributes your schedule columns should capture.

Anstey Horne's UK guide for housing providers states that fire stopping must maintain the same fire resistance as the element it penetrates (for example REI 60), and describes three compliant penetration approaches: proprietary tested systems, which it prefers; a diameter-limited approach for some plastic and metal pipes; and high-melting-point metal sleeving installed to tested geometry. For the quantity surveyor, this means two similar-looking crossings can carry different items, so describe each by approach.

Step 4: Count and measure

Count openings, not pipes

Three pipes through one sleeved opening is normally one fire stopping system, priced for the opening size and the most onerous penetrating item. Counting each pipe overstates the quantity. Counting each tray by the number of cables inside does the same. Price a tray as a tray.

Separate new from existing

On refurbishment, the NFRC's technical bulletin on firestop to party and compartment walls (November 2025) notes that the requirement applies to refurbishment as well as new build. Mark each row new, existing-to-be-made-good, or opening left by removed services. Remedial work is a different scope and a different price from first-time installation.

Measure linear joints by length

Measure joints from partition plans and sections along the compartment line, and state the joint width and the depth of the seal where it is shown. The NFRC bulletin describes the common party-wall firestop as flexible or semi-flexible stone wool compressed into the void above the wall and into the batten space, installed wider than the wall to allow for tolerances. Where your detail resembles that, describe the item by what is installed and the junction it closes, not just by length.

Capture spacing constraints

Rockwool's guide gives distance requirements for seals: the distance between aperture edges of penetration seals in a building element shall be as tested or 100 mm, and at least 200 mm between a penetration seal and any other penetration such as a door. Service supports should be installed as a reflection of the fire test (ASFP Advisory Note 8). On congested risers and plant rooms, these rules decide whether two services can share an opening, so they change your count. Flag crowded areas for review rather than assuming the drawn layout works.

Capture spacing constraints

Do not miss the small items

Small conduits, data cables, cast-in devices at floor drains, and openings that appear only on one of two coordinated drawings are the usual under-counts. The overlay method in the schedule, compartment line first, then every service crossing it, is what catches them.

Step 5: Handle uncertain or missing information

Fire stopping drawings are often incomplete at tender stage. A workable approach:

  1. Record the assumption in the row. State what you assumed (for example, "60-minute wall, plastic pipe up to a stated diameter") so the basis is visible.
  2. Use a provisional quantity where the count depends on services design, and say so in the bill.
  3. Raise a query tied to the tag, not a general question about fire stopping.
  4. Log revisions against rows. When a drawing changes, update the affected tags and keep the previous count visible.

Avoiding repeated counting across revisions and between trades matters as much as finding the missing items. Our guide on avoiding double counting in a take-off covers the discipline, and the eight-step audit-ready workflow shows how to keep each stage checkable. Where drylining forms the compartment, the fire stopping at its heads and junctions links to the partition quantities in the drylining takeoff method.

Common errors at a glance

ErrorEffect on the billFix
Counting every pipe, not every openingOverstated numbered itemsCount openings; price for the worst-case penetrant
Measuring every gap, not only rated boundariesInflated scopeStart from the compartmentation drawings
Generic "fire sealant" descriptionUnclear price basis, disputes laterEnter the tested system reference
Mixing new and existing penetrationsWrong rates, wrong scopeStatus column in the schedule
Overlooking joints at head of wall and floor edgesUnder-measured linear workMeasure from partition plans and sections
Ignoring spacing rules in congested areasCounts that cannot be built as drawnFlag crowded risers and plant rooms

Where QuantiFlow fits

QuantiFlow is in development. It is designed to read construction drawings and produce a draft Bill of Quantities for a quantity surveyor to review and sign off. For a fire stopping schedule, the judgement stays with you: which boundaries are rated, which system applies, what to carry as provisional. You can see the plans on the QuantiFlow site, which lists Solo, Business and Enterprise options.

Quantiflow

If you also work on extensions and refurbishments, the house extension takeoff checks show how a reviewable draft is audited line by line.

FAQ

What counts as fire stopping in a bill of quantities?

It covers the sealing of openings, joints and gaps in fire-resisting walls and floors: service penetrations, linear joints, and junctions with structure and doors. Cavity barriers and similar items may be billed separately depending on the measurement approach in use. Describe each item by element, fire resistance period and system reference.

Should I measure fire stopping per pipe or per opening?

Per opening. Several pipes through a single sleeved opening are normally one system, priced for the opening size and the most demanding penetrating item. Record what passes through each opening in the schedule so the pricing basis is visible.

Which drawings do I need to take off fire stopping?

You need the fire strategy or compartmentation drawings, floor plans, partition layouts and sections for joints, and the services and structural drawings for the crossings. The door schedule covers doorsets. Without the fire strategy, you cannot reliably tell which gaps need sealing.

Does fire stopping apply to refurbishment work?

Yes. The NFRC's November 2025 bulletin on firestop to party and compartment walls notes that the requirement applies to refurbishment as well as new build. Openings left after services are removed also need sealing.

Sources

This article is for general information only and is not professional, legal or commercial advice. Quantity surveying decisions should be taken by a qualified professional with reference to the specific project, drawings and contract in question. Content is produced with AI assistance and reviewed before publication. QuantiFlow Ltd accepts no liability for reliance on it.