Quantities follow the design. Under the RIBA Plan of Work 2020, you work from areas and counts at Stages 0 to 2, measured sub-elements at Stage 3, and full NRM 2 measurement at Stage 4, when the Bill of Quantities (BoQ) is prepared from technical design information. From Stage 5 onwards the quantities are used, checked and remeasured rather than created. The rest of this guide sets out what is measurable at each stage, which RICS rule governs it and where timing shifts with the procurement route.
TL;DR
- The RIBA Plan of Work 2020 has eight stages, numbered 0 to 7. Stages 0 to 4 are where most quantity and cost work is produced.
- Early stages use RICS NRM 1: order of cost estimates, then Formal Cost Plans 1, 2 and 3. Detailed measurement and BoQs use NRM 2.
- A BoQ needs the information that comes out of Technical Design: specification, drawings and schedules. Measuring earlier means measuring assumptions.
- Procurement route moves the timing. Under design and build, the contractor side may prepare the quantities.
- After contract award, quantities support valuations, variations and the final account.
Table of Contents
- The eight RIBA stages and the quantity work that goes with them
- Stages 0 and 1: estimates from areas, not drawings
- Stage 2, Concept Design: the first elemental quantities
- Stage 3, Spatial Coordination: sub-elements and coordinated design
- Stage 4, Technical Design: where the Bill of Quantities is measured
- Stages 5 to 7: quantities in use
- Why timing moves with procurement
- How accurate should each stage be?
- Where drawing-based takeoff software fits
- Practical checklist before you start a BoQ
- FAQ
- Sources
The eight RIBA stages and the quantity work that goes with them
The Plan of Work organises briefing, design, construction and use into eight stages, each with outcomes, core tasks and information exchanges. The 2020 edition names them:
| Stage | Name | Typical quantity and cost output |
|---|---|---|
| 0 | Strategic Definition | Rough order of cost estimate |
| 1 | Preparation and Briefing | Order of cost estimate, option costs |
| 2 | Concept Design | Elemental cost estimate, Formal Cost Plan 1 |
| 3 | Spatial Coordination | Formal Cost Plan 2 |
| 4 | Technical Design | Formal Cost Plan 3, then BoQ and tender pricing documents where the route needs them |
| 5 | Manufacturing and Construction | Valuations, variations, cost reporting |
| 6 | Handover | Final account |
| 7 | Use | In-use cost review |
The cost column follows RICS NRM 1 (October 2022), Table 1.1, which maps estimating and cost planning to the RIBA stages. NRM 1 covers order of cost estimates and cost plans. NRM 2 covers detailed measurement for BoQs and quantified schedules. If you want the background on the second standard first, our guide to NRM2 and how it measures building works covers it.
One point trips up many people searching for stage numbers. Older material uses lettered work stages (A to L) from the pre-2013 plan. The 2020 plan uses numbers, so a letter in an old specification or appointment document needs translating before you apply the table above.
Stages 0 and 1: estimates from areas, not drawings
At Stage 0 the project is a need and a site. There is no design to measure. NRM 1 pairs this stage with a rough order of cost estimate, and Stage 1 with an order of cost estimate that can include option costs.
The quantity you measure is usually a single, high-level one. A TU Dublin study of cost estimates for mechanical and electrical services (2015) describes the order of cost estimate as gross internal floor area multiplied by a cost per square metre benchmark. That is the typical shape of an early estimate: one measured area, one benchmarked rate and a stated set of assumptions.
What matters here is the assumptions register. With so little measured, the estimate is only as good as what you record about site conditions, specification level and exclusions. When the design moves, you can then see which assumption changed and by how much.
Stage 2, Concept Design: the first elemental quantities
Stage 2 is where quantity work becomes structured. The design team develops the architectural concept, structural strategy and services approach, and the cost consultant prepares Formal Cost Plan 1 under NRM 1. RIBA's Stage 2 checklist asks the architect to give the cost consultant the information needed for the initial cost plan and cash flow projection, and to discuss the cost effect of major design decisions with the client before they are taken.
The measurable items are elemental and broad: areas of external wall and roof, flights of stairs, lift counts, window and door areas taken from plans and elevations. They are measured from concept plans, sections and elevations at small scale, often with dimensions that are not yet fixed.
Two habits keep Cost Plan 1 useful:
- Measure to a consistent elemental structure. The same breakdown at Stages 2, 3 and 4 lets you compare plans and explain movement.
- Write down what the drawing does not show. Foundation type, cladding specification and services allowances are normally assumptions at this point. Flag them as such.
Design teams increasingly work from digital models at this stage, and standard components arrive with their own data. BIM object libraries explain how designers find and check that data. Where objects carry dimensions or areas, they can feed an early area schedule, though you still need to confirm what the numbers represent before they go into a cost plan.
Stage 3, Spatial Coordination: sub-elements and coordinated design
The answer to the common question "what is RIBA Stage 3 design?" is that it is Spatial Coordination, the stage in which architectural, structural and services designs are brought together into a coordinated whole. NRM 1 pairs it with Formal Cost Plan 2.
The practical change for quantities is the level of breakdown. Where Cost Plan 1 might carry one external walls element, Cost Plan 2 splits it into sub-elements: for instance curtain walling, rendered blockwork and stone cladding, each with its own measured quantity and cost target.
The public-sector guidance from Scottish Futures Trust describes the same expectation in its stage-based validation for spatial definition: a spatially coordinated architectural and engineering design aligned to an elemental cost plan, with design development, outline specifications and cost exercises reconciled to the project budget.
Typical Stage 3 measuring jobs include:
- Wall, floor and roof areas by construction type, rather than by a single element.
- Door and window counts by type from draft schedules.
- Structural quantities from the coordinated structural design, such as slab areas and frame tonnage allowances.
- Reconciling the plan to the budget and recording the reasons for any change since Cost Plan 1.
For most SME projects the planning submission also lands in this stage, so Cost Plan 2 often serves as the cost check before the planning application goes in.
Stage 4, Technical Design: where the Bill of Quantities is measured
Stage 4 is where the question of quantities is answered in full. The design is complete enough to specify and detail, and the quantity surveyor produces Formal Cost Plan 3 and, where the procurement route calls for it, the BoQ and tender documents.
What NRM 2 expects you to have
NRM 2 states that preparing a BoQ needs the information produced by the technical design and production information stages. That means:
- A prescriptive specification naming materials and workmanship in as much detail as possible.
- General arrangement drawings: block plan, site plan, plans, sections and elevations.
- Component and schematic drawings, and record drawings where relevant.
- Schedules: room data sheets, door and window schedules, bar bending schedules, and drainage, fittings, luminaires and controls schedules.
The edition and rule details are in NRM 2 from RICS, the second edition (effective 1 December 2021 and reissued October 2022).
RIBA's own Stage 4 checklist lines up with this. Task 4.5.11 directs the architect to prepare information for specifications, schedules and bills of quantities, and to supply the cost consultant with specification notes for the work sections, preliminaries information, location drawings, component drawings and drawn schedules. Preliminaries information includes the form of contract, method statements, health and safety, provisional sums and named subcontractors.
If any of those are missing when you start measuring, the BoQ will carry the gap. Provisional sums, approximate quantities and clearly stated assumptions are how NRM 2 lets you deal with that honestly. Our guide to the role of drawings in quantity measurement covers what a measurable drawing set looks like.
What a BoQ contains
A BoQ usually comprises a form of tender, summary, preliminaries, measured works, non-measurable works, provisional sums, contractor-designed works, risks, credits, dayworks (provisional) and annexes. The quantities and descriptions in the measured works are determined under the tabulated rules in NRM 2 Part 3. RICS defines the BoQ as a list of the items making up the component parts of a building, with detailed descriptions and quantities, so that contractors can tender efficiently and accurately. After award it provides the basis for valuing executed and varied work.
The preliminaries section deserves attention at this stage because it draws on the Stage 4 information listed above. Our note on NRM2 preliminaries and contractor breakdowns goes into how to structure it.
A worked example at SME scale
Take a single-storey rear extension. At Stage 2 you might carry external wall area, roof area and a count of openings, priced at elemental rates. At Stage 3 the external wall splits into brick and block cavity wall and any glazed section. At Stage 4, with structural calculations, a wall build-up and a window schedule, you measure to NRM 2: excavation, concrete, masonry, roof structure, coverings, windows and doors, finishes and services items, each with a described quantity. For a fuller walk-through of that sequence, see our house extension takeoff checks.
Stages 5 to 7: quantities in use
Once on site, quantities change role. RIBA's Stage 5 checklist calls for records of site visits, progress inspections and goods and materials checks, and for liaison with the cost consultant on remeasurement, valuations and variations. The architect generally inspects the work against the drawings and specification and certifies staged payments to the contractor, as RIAS describes the process.
For the QS, that means:
- Interim valuations measured against the BoQ items and the programme.
- Variations priced from the original BoQ rates where the contract allows, and recorded against the instruction that caused them.
- Cost reporting and cash flow forecasts updated as instructions arrive.
- Final account at Stage 6, with defects costs and retention release.
At Stage 7, in-use cost data can inform feasibility work on future projects. RIBA's Plan for Use Guide also advises that requirements for contractors to issue asset information be set out in the tender and specification documents at Stage 4. Your BoQ preliminaries are one place to carry that requirement.
The measured BoQ is the reference for everything above. Clear item descriptions and traceable measurements at Stage 4 make valuations and variations quicker to agree later.
Why timing moves with procurement
The table above shows the traditional sequence. Real projects vary, and NRM 2 says so. The RICS text describes the RIBA Plan of Work as procurement-neutral: contractor appointments can come before or during the design stages, and tendering and award vary with the route. It adds that the RIBA stage sequence may need to be varied or overlapped to suit the procurement method.
The consequences for quantities:
- Traditional lump sum with a client-side BoQ. The client's QS measures at Stage 4 and tenders on firm or approximate quantities. This is the sequence described above.
- Design and build. The main contractor or works package contractors may prepare the quantities. Your Stage 4 work as an employer's QS is then more likely to be the employer's requirements, a cost plan and a pre-tender estimate.
- Two-stage routes. The contractor joins during design, so pricing documents grow alongside the design rather than after it.
The NRM 1 table also places the pre-tender estimate, tender pricing documents and post-tender estimate at the Contractor Engagement point rather than at a fixed RIBA stage, which is how the standard handles these differences.
The accuracy of the BoQ depends on the quality of the information supplied by the client, designers and project team. Where a design is still moving at tender, you have two choices: measure only what is defined and use provisional sums or approximate quantities for the rest, or hold the tender until the information is ready.
How accurate should each stage be?
There is no single accepted band that applies to every project, and a published range is only a guide. As one example, the TU Dublin study cited earlier reported accuracy bands for HVAC and electrical services estimates of under 25% at Stage 2, under 15% at Stage 3 and under 5% at Stage 4, using the older stage naming. Treat that as an illustration of the direction: bands tighten as the design firms up. It is not a target for your own estimates on any particular job.

What you can control is the audit trail: which drawing revision each quantity came from, which rule applied and what you assumed where information was missing. Our guide to NRM2 takeoff rules that keep a BoQ audit ready sets out how to keep that record.
Where drawing-based takeoff software fits
By Stage 4 the largest block of time is usually the measurement itself, reading dense PDF drawings and cross-checking them against schedules and the specification. QuantiFlow is in development as a tool that reads construction drawings and produces a draft Bill of Quantities for a quantity surveyor to review and sign off. The measurement rules, the item descriptions and the sign-off stay with you. You can read more at quantiflow.co.uk.
Practical checklist before you start a BoQ
Before opening the first drawing at Stage 4, confirm:
- The drawing register and revision of every drawing you are measuring from.
- That the specification matches the drawings, and note conflicts as queries.
- That schedules for doors, windows, finishes and services exist and agree with the plans.
- That preliminaries information (contract form, method statements, health and safety, provisional sums, named subcontractors) has been supplied.
- The procurement route, so you know whether you are producing the quantified BoQ, an unquantified one or a schedule of work.
- What is still provisional and how each item will be described in the bill.
FAQ
What is RIBA Stage 2 called?
Stage 2 is Concept Design in the RIBA Plan of Work 2020. The design team develops the architectural concept, structural strategy and services approach. The cost consultant prepares Formal Cost Plan 1 under RICS NRM 1.
What is RIBA Stage 3 design?
Stage 3 is Spatial Coordination. The architectural, structural and services designs are coordinated, and the cost plan becomes Formal Cost Plan 2, which measures sub-elements such as individual wall types instead of a single external walls element.
What is RIBA Stage 4 in construction?
Stage 4 is Technical Design. The specification, detailed drawings and schedules are completed. On a traditional route this is when the QS refines the cost plan to Formal Cost Plan 3 and measures the Bill of Quantities to NRM 2.
What are RIBA Stage 5 drawings?
Stage 5 is Manufacturing and Construction. Drawings at this stage are the construction information the contractor builds from, along with any further information the contract requires. For the QS, it is the basis for valuations, variations and remeasurement.
At which stage should a Bill of Quantities be prepared?
On a traditional route, at the end of Stage 4, once technical design information is complete. NRM 2 notes that the stage sequence can vary with procurement, so check your route and appointment documents.
Sources
- RIBA Plan of Work
- RICS NRM 1, October 2022
- RICS NRM 2, October 2022
- RIBA Stage 2 checklist
- RIBA Stage 4 checklist
- RIBA Stage 5 checklist
- RIBA Plan for Use Guide 2021
- Scottish Futures Trust, stage-based validation 3, spatial definition
- RIAS, The Construction Process
- TU Dublin, defining cost estimates for mechanical and electrical services (2015)
Recommended
- As-Built Quantities: What They Are and How QSs Measure Them
- BIM Quantity Extraction: A UK QS Guide to Reliable Quantities
- Specification Changes and Quantities: A QS Re-Measure Guide
- Control Price Risk with Approximate Quantities for UK QSs
This article is for general information only and is not professional, legal or commercial advice. Quantity surveying decisions should be taken by a qualified professional with reference to the specific project, drawings and contract in question. Content is produced with AI assistance and reviewed before publication. QuantiFlow Ltd accepts no liability for reliance on it.