Change control for quantities means that every alteration to drawings, scope or site conditions is logged, measured against the right drawing revision, valued under the contract and approved before it reaches the cost report or final account. In practice it comes down to four things: a numbered register, a clean remeasure, a valuation that follows the contract, and a trail that shows who instructed what and when. This guide sets out each one for QSs at small and mid-sized firms.
TL;DR
- Register every change with a discrete number, whoever raises it, and update the register at least monthly, as RICS' 2024 change control guidance sets out.
- Measure omissions from the old drawing and additions from the revised drawing, and record which revision each line came from.
- Value changes as the contract directs: tender rates for similar work under JCT, defined cost under NEC.
- Carry anticipated but uninstructed changes in the cost report, labelled as such.
- Agree all variations before the final account is settled.
Table of Contents
- What change control means for quantities
- What actually triggers a change in measured quantities
- A step-by-step routine for controlling quantity changes
- Valuing a quantity change: what the contract says
- How JCT and NEC change the process
- Registers, approvals and the audit trail
- Checks that prevent omissions, duplication and disputes
- Where drafting tools fit
- FAQ
- Sources
What change control means for quantities
Change control is the process that governs anything that can alter the timescale, cost or scope of a project. That is how RICS' 2024 Change control and management guidance defines it. The same document describes the bill of quantities (BQ) as a list of items with detailed descriptions and firm quantities of the work, which is eventually rated and used as a cost control document.
That last point matters. The BQ is not just a pricing tool at tender. Once the contract is signed it becomes the yardstick against which every change is measured. RICS' NRM2 (October 2022) says a firm bill gives a good basis for cost control because the direct cost of change can be assessed by reference to the BQ rates, and that the BQ is the basis for valuing work executed for interim payments.
So for a QS, change control on quantities is a narrower job than the project-management version of the term. You are answering three questions for each change:
- What has been added, omitted or altered, and against which drawing revision?
- What is the measured difference in quantity, and which BQ items does it touch?
- How does the contract say it must be valued, and who must approve it?
Most disputes at final account come from a weak answer to one of those.
What actually triggers a change in measured quantities
Changes rarely arrive labelled as changes. The Hong Kong Institute of Surveyors' Practice Note PN06 lists the forms they commonly take, and the list will be familiar to any UK QS:
- revised drawings issued to the team
- architect's, project manager's or engineer's instructions
- drawing amendment notifications
- site instructions
- verbal instructions followed by a confirmation
The practice note advises checking whether your contract accepts each of these as a formal instruction. Under a JCT form, for example, a drawing revision sent by email may be a design development rather than an instruction that changes the contract sum. The distinction decides whether you value it or not.
The RICS cost reporting guidance note (1st edition) adds a forward-looking category: anticipated instructions. It expects the QS to review contractor instruction requests, drawing revisions, specification revisions and programme delays that sit at the client's risk, make a suitable cost allowance, and identify clearly in the cost report that these are anticipated and not yet formally instructed.
Errors in the bills are changes too
Change is not only the client altering their mind. Under the JCT Standard Building Contract with Quantities, RICS' Valuing change explains that the employer holds the risk that the bill quantities are accurate. Errors in quantity or in the method of preparation are corrected and treated as variations. A measurement slip you find in the tender bill therefore becomes a change item to record and value, not something to absorb quietly.
A step-by-step routine for controlling quantity changes
The routine below combines the RICS and HKIS guidance into a sequence a small team can run on every job.
1. Log the change on receipt
Register every change on a suitable register with a discrete number, whoever raised it. The Scottish Government's Project Initiation and Business Case Handbook (2019, Chapter 16) suggests recording the date received, the originator, a description and any dependencies. Add the drawing numbers and revision letters affected.
Where it goes wrong: changes held in an inbox or a site diary and never numbered. You cannot later show the client when the instruction arrived or what it covered.
2. Confirm it is a valid instruction
Check that the instruction comes from the person the contract empowers. C-Link's guide to valuing variations notes that under JCT contracts, work carried out without an instruction risks non-payment, which is why the HKIS advice to attach confirmation letters to verbal instructions and file them together carries over directly to UK practice.
Where it goes wrong: valuing site work that nobody with authority instructed.
3. Identify the affected drawings
Check the drawing register for the latest revision of every affected drawing. The HKIS note recommends highlighting the changes on the new drawings so the scope of the change is visible at a glance.
Where it goes wrong: measuring from a superseded revision, or from a revision that changed something else as well. Our guide to remeasuring after revisions in five NRM2 steps covers that stage in more detail.
4. Remeasure omissions first, then additions
PN06 advises measuring omissions from the old drawings first and additions from the revised drawings. This keeps the net effect honest: you cannot double-count an element that appears on both sheets if you have measured the deduction from the original and the addition from the new.
Where it goes wrong: measuring only the new drawing and treating its full quantity as the variation, which overstates the change.
5. Measure on the same basis as the bills
Where the contract has a bill of quantities, a change should be measured by the same rules of measurement used to build the BQ rates. A variation to excavation priced at a cubic metre rate must be measured in cubic metres, not converted to a linear rate. Your measurement rules should match the method adopted for the bill, which for most UK building work is NRM2.

6. Value, record and report
Value the change under the contract (next section), record the status, and carry it into the monthly cost report. RICS cost reporting guidance recommends monthly updates, with agreed valuations identified as such and unagreed valuations shown separately.
Valuing a quantity change: what the contract says
The measurement is only half the job. The same quantity can produce very different values depending on how the contract tells you to price it.
Tender rates come first under JCT
RICS' 2024 guidance states that variations are often valued using the rates and prices in the contractor's tender, provided the work is of similar nature and carried out in similar conditions. Those rates apply even if they turn out higher or lower than commercial rates available elsewhere.
RICS' Valuing change (June 2010) describes the JCT Valuation Rules as a sliding scale. Where the work is of similar character to the contract documents, the valuation is consistent with the priced document, with a fair allowance for changes in conditions or quantity. That is the process often called re-rating or star rating. Work that is not of similar character is priced at fair rates and prices.
Character is about specification, not only labour
The same guidance explains that the character of an item is what distinguishes it from other, possibly similar, specifications. Stone bedded in the same material with the same labours can cost very differently depending on the material specification. When you decide whether a changed item is similar to a billed item, compare the specification, not just the operation.
What to assemble for each change
The 2024 RICS guidance expects the QS, with the project manager and the contract administrator, to assemble documentation for each change item monthly. That includes:
- substantiation of the quantities or lump sums and the rates, with star rates where contract rates cannot be applied
- BQ references and build-ups
- quotations, purchase orders and invoices
- a breakdown of labour, materials, plant and other costs for the cost report
- the relevant drawings and specifications
- preliminaries, insurances and bonds, if affected
- a revised construction programme
- the status: agreed, under consideration, more information requested or rejected
A quantity change often drags preliminaries and programme with it, so look beyond the measured items.
Approximate quantities
Where the bill contains approximate quantities, the question is whether the contract quantity was a reasonable forecast. If it was, the BQ rate applies. If not, the rate is the starting point and a fair allowance is made for the difference. Under the JCT form with approximate quantities, RICS notes that the QS must remeasure the work and adjust the bills progressively, except for Contractor's Quotation work or fixed, non-remeasurable Contractor's Design Portion work.
How JCT and NEC change the process
Before setting up any register, read how your contract treats quantity change. The approach differs.
| Point | JCT with quantities | NEC Option B |
|---|---|---|
| Risk of bill quantity errors | Employer; corrections treated as variations | Differences between final and stated quantities can be compensation events |
| Basis of valuation | Contract rates for similar work, fair rates otherwise | Defined cost plus fee, not tender rates |
| Who instructs | Architect or contract administrator | Project manager |
RICS' Valuing change (1st edition, March 2025) sets out that under NEC Option B the compensation events include a difference between the final total quantity and the quantity stated in the bills, an inaccurate quantity that changes the Defined Cost per unit, a bill item making up more than 0.5% of the Prices at the Contract Date, correction of departures from the adopted method of measurement, and correction of an inconsistency between the bills and another document.
The practical point for a small firm: the same drawing revision can be a routine variation under one contract and a compensation event with strict notification timescales under another. Put the contract form on the first line of your change register.
Registers, approvals and the audit trail
The Scottish Government handbook says changes and the decision process should be recorded to provide an audit trail for accountability. It lists the documents to maintain: a document control register, a change request form, a change control register, a cost plan recording the impact of changes, and the programme.
RICS' 2024 reporting requirements add that you should distribute and file copies of change documents, including minutes of change board meetings, and follow up to make sure all affected drawings and specifications are updated and reissued. Using document approval software can help keep instructions, signatures and revised drawings in one dated record, which suits a team that otherwise chases approvals by email.

Keep approval proportionate
The handbook recommends setting approval authority levels in the project execution plan and conducting approval at the most appropriate level, because a hierarchical process delays decisions and affects cost and programme during construction. It also advises checking for aggregation of delegated authority: a team member who can approve changes up to £10,000 could approve ten changes totalling £100,000. Set a cumulative limit as well as a per-change one.
Link each line to its revision
An audit trail is only as good as the link between a measured quantity and the drawing it came from. If each BoQ line records its drawing revision, any question about a variation can be answered by opening the source. We cover this in linking each BoQ line to its drawing revision, and the wider routine in an eight-step audit-ready takeoff workflow.
Checks that prevent omissions, duplication and disputes
A short checklist, run monthly alongside the cost report, catches most problems:
- Register integrity: is every change numbered, dated and given a status? RICS asks for the register to be updated at least monthly.
- Acknowledgement: have you sought acknowledgement of change submissions, so contract timing mechanisms are observed?
- Revision match: does each measured quantity cite the latest valid revision of the drawing?
- Omission and addition pairing: has every addition been checked for a matching omission, and the reverse?
- Instruction cover: is there a written instruction for each change, issued before work began where possible?
- Final account: are all variations agreed before the final account is settled?
For subcontract work, add one more check: every downstream variation should correspond to an upstream instruction from the client, otherwise you may be paying for something you cannot recover.
Where drafting tools fit
The slowest part of a change is usually the remeasure: finding the revised sheets, comparing them with the old ones and re-extracting quantities. QuantiFlow is in development. It reads construction drawings and produces a draft Bill of Quantities for a quantity surveyor to review and sign off, with the judgement on what is a valid change and how to value it staying with you. You can see the current plans on the QuantiFlow site.
FAQ
What is change control in quantity surveying?
It is the process of recording, measuring, valuing and approving every alteration to scope, drawings or conditions that affects quantities or cost. RICS defines change control as the process or processes that can lead to alteration of the timescale, cost or scope of a project. For a QS, the output is an updated register, remeasured quantities and a valuation consistent with the contract.
How do you value a variation to a bill of quantities?
Follow the contract. Under JCT forms with a priced bill, use the contract rates where the work is of similar character and conditions, make a fair allowance where quantity or conditions differ significantly, and use fair rates and prices where the work is not similar. NEC contracts assess compensation events on defined cost plus fee instead.
Do I need a written instruction before valuing a change?
Yes, wherever the contract requires it. Under JCT contracts, work carried out without an instruction risks non-payment, so the safe routine is to have instructions issued in writing, or verbal instructions confirmed in writing and filed with the measurement.
How often should the change register be updated?
At least monthly, according to RICS' 2024 guidance, which also asks for change documentation to be assembled monthly. The RICS cost reporting note recommends monthly cost reports, matching the UK practice of valuing work monthly.
Sources
- RICS, Change control and management (2024)
- RICS, New rules of measurement, NRM2 (October 2022)
- RICS, Valuing change (1st edition, 2010)
- RICS, Valuing change (1st edition, March 2025)
- RICS, Cost reporting guidance note (1st edition)
- Scottish Government, Project Initiation and Business Case Handbook, Chapter 16 (2019)
- HKIS, Practice Notes for Quantity Surveyors, PN06
Recommended
- Specification Changes and Quantities: A QS Re-Measure Guide
- Keep Tender Quantities Within ±5%: NRM2 Workflow for UK QS
- Remeasure After Revisions: 5 NRM2 Steps for UK QSs
- UK QSs: Stop NRM2 Measurement Mistakes With Practical QA Steps
This article is for general information only and is not professional, legal or commercial advice. Quantity surveying decisions should be taken by a qualified professional with reference to the specific project, drawings and contract in question. Content is produced with AI assistance and reviewed before publication. QuantiFlow Ltd accepts no liability for reliance on it.