Value Engineering and Quantities: A QS Guide to Getting Both Right

November 23, 2026
Value Engineering and Quantities: A QS Guide to Getting Both Right

Value engineering only works when the quantities underneath it are sound. Every option put to a design team is a claim about cost, and that claim is only as good as the measured quantities, the rates applied to them and the record of what changed. This guide sets out how value engineering is defined in UK practice, where measurement sits in the process, how to measure and price a proposed change, and how to keep the audit trail that protects you and your client.

Quantiflow
quantiflow.co.uk
Build Value Decisions on Sound Quantities
QuantiFlow turns architectural drawings into NRM2-aligned takeoffs and structured Bills of Quantities, supporting measured, priceable cost decisions.
Visit

TL;DR

  • Value engineering is a structured review that improves the ratio of benefit to cost. It is not the same as removing scope or lowering the specification to hit a number.
  • Quantities are the evidence base: the bill of quantities and cost plan give you the baseline against which every option is priced.
  • Measure the change as a net difference. Quantify what is omitted and what is added, then revisit rates, preliminaries and risk allowances.
  • The later a proposal arrives, the more it costs and the less it can achieve, so bring the QS in early.
  • Keep every revision traceable: what was measured, from which drawing issue, at what rate, and who approved it.

Table of Contents

What value engineering means in UK practice

The RICS practice information on value management and value engineering describes value engineering as a structured, auditable, multidisciplinary process. It focuses on eliminating unnecessary cost to improve the ratio between benefits and costs. Value itself is the ratio of benefit (outputs) to the cost or effort (inputs) needed to achieve it.

The same guidance is clear about what value engineering is not. It does not mean removing necessary cost by reducing scope, omitting work items or downgrading the specification below the performance level the client requires. It also recognises that improving whole-life value can sometimes need extra initial capital expenditure.

That distinction matters in practice. Homebuilding (March 2026) contrasts cost-cutting, which is typically reactive and happens once a project has exceeded budget, with value engineering, which is proactive and aims to remove unnecessary cost while preserving performance, durability and quality. It also links late cost cutting to the absence of early cost advice from a quantity surveyor.

A practical test for each option

For every option on the table, ask whether it delivers the same function for less, or simply costs less. Writing Surveyor Success, Courage Oseghale makes the same point: an option justified only by being cheaper is not value engineering, and the QS should say so in the cost report because the client carries the risk if quality erodes. If you can state the function in a short verb and noun pair ("keep out water", "support floor loads"), you can compare solutions fairly. If you cannot, the option is probably a cut.

Why the quantity surveyor sits at the centre

RICS guidance notes that the quantity surveyor is the central professional concerned with project costs and sits outside the traditional design disciplines. That position gives the QS a natural role in helping the whole team manage value. RICS's standard form of consultation for quantity surveyor services (May 2022) lists, among the QS duties, preparing cost analyses and facilitating, setting up and managing value engineering exercises.

Writing in the RICS Construction Journal, Keith Owen argues that the QS is well placed to provide and manage value as well as cost and change control, but that it must be done carefully, without affecting the functions. The Property Research Trust's comparative study (September 2015) observes that the QS role has widened from cost planning and bill preparation to whole-life costing, value management and risk analysis.

For an SME practice, this has a practical consequence. You are often the only cost professional in the room, and you will be asked what an option saves before anyone has time to check it. The quality of your quantities decides whether your answer holds.

How quantities, estimates and bills support the review

Value engineering starts from a baseline. RICS's Commercial Management of Construction standard says the process relies on the project estimate and budget as its starting point, and is best undertaken between project inception and detailed design, with all alternatives assessed holistically, including post-construction maintenance costs.

The RICS New Rules of Measurement form a three-volume suite: NRM 1 for cost estimating and cost planning of capital works, NRM 2 for detailed measurement of building works, and NRM 3 for maintenance works. Each does a different job in a value engineering exercise:

  • Early stages: NRM 1 frames the cost plan. It introduces functional units, such as a unit representing the prime use of a building, which let you compare options on a like-for-like basis.
  • Detailed stages: NRM 2 describes a bill of quantities as a coordinated list of items with descriptions and quantities. It supports pre-tender and post-tender estimates, cost planning, pricing variations and interim valuations. Its cost data can also be reprocessed into elemental analyses and unit rates for future estimates.
  • Cost control: NRM 2 states that the firmer the bill, the better it works as a means of financial control, because the direct cost of change can be assessed against the bill rates.

That last point is the heart of the matter. A firm bill gives you rates you can reuse to price a proposed change. A loose one leaves you arguing about what the baseline was. If you want a refresher on the different forms of bill and when each applies, our guide to the types of bills of quantities covers them.

Who takes part, and when

The RICS Construction Handbook describes a first functional analysis to inform the brief at option appraisal, a review at outline design and a functional analysis of solutions at scheme design using cost planning and life-cycle costing. It recommends an experienced value management facilitator. Participants should represent the client, the building users, the design team (designer, engineers and quantity surveyor) and, where applicable, the contractor, each with authority to make decisions at the workshop.

A peer-reviewed 2020 study of the QS role in value management workshops concludes that the QS should be introduced at the earliest opportunity. The reason is time: you need room to review project costs and alternatives before the team agrees a strategy.

In practice that means three things for the QS:

  1. Ask for the brief and the client's priorities before the workshop. RICS's commercial management standard stresses that the brief should define both priorities and value.
  2. Arrive with a priced baseline, not an opinion. A cost plan or draft bill at a known drawing issue gives everyone the same starting figure.
  3. Come with cost data for alternatives, including alternative construction techniques, so the team can compare options rather than guess.

Measuring and pricing a proposed change

Once an option is shortlisted, the job becomes measurement. RICS's Valuing Change guidance (reissued March 2025) says additions and omissions are valued by quantifying the change in scope and applying rates for identical or similar work. You then consider the effect on preliminaries, risk allowances, design fees, overheads and profit. Where the work is not similar, you form a new rate with adjustments for differences in conditions, character or quantity.

A checklist for each option

  • Fix the baseline. Record the drawing issue and bill revision you are measuring against.
  • Measure both sides. Quantify the omitted work and the added work separately. Netting them in your head is where errors start.
  • Check for double counting. Substitutions often overlap, for example a finish measured in both the omitted and added items. Our note on avoiding double counting in a take-off sets out a routine.
  • Revisit economies of scale. Valuing Change asks the QS to reconsider volume discounts, labour efficiencies and supervision ratios when quantities change. A smaller quantity may not carry the original rate.
  • Look beyond the element. Check preliminaries, programme, design fees and any knock-on work.
  • State exclusions and assumptions. Write down what the figure does not cover.

An illustration

This is a hypothetical example, not a real project. A bill includes 400 m² of one external wall build-up, and the team proposes an alternative that performs the same function. You measure the 400 m² omitted at the bill rate. You then measure the alternative, including any additional items it needs such as extra fixings, a different support detail or longer erection time. If the new build-up needs a more complicated junction at every opening, the saving on the wall area can be absorbed by the extra cost at the junctions.

Measured wall quantities and added costs compared

The RICS value management guidance makes exactly this point with a structural example. A design that minimises the size of, and raw materials in, each beam and column can reduce overall value if it needs far more complicated connections and site management that raise installation costs. Value has to be assessed across the whole asset, not element by element.

When the item is unusual, the choice between building up a rate and using a library rate matters. Our piece on rate build-up versus library rates looks at how QSs approach risky items.

Specification wording changes the price

NRM 2 distinguishes prescriptive specifications, which name materials and workmanship and are required to prepare a firm bill, from performance specifications, which describe objectives and shift design responsibility to the contractor. When a substitute product is proposed, the specification type decides who carries the performance risk. A. Proctor Group's Will Jones notes that swapping in a cheaper product needs a good understanding of the effect on performance.

The risk of late change

RICS's value management guidance shows that the cost of change increases, and the impact of change decreases, as a project progresses. Late value engineering therefore has diminishing benefit. It also carries more risk.

NRM 2 warns that insufficient or poorly described specification information can mislead contractors and result in variations and time- and cost-related claims. It also explains that risks which cannot be designed out in time must be managed by transfer (with a risk premium paid by the client), sharing or retention. A bill's risks section lists the residual risks the client wishes to transfer, and the contractor prices them as a lump sum.

Under the JCT Standard Building Contract with Quantities, Valuing Change explains that the priced bill is a contract document defining quality and quantity of work. The employer holds the risk that the quantities are accurate against the stated measurement rules, and quantity errors are corrected and treated as variations. A late change that rests on a mismeasured baseline therefore lands on the client, and the QS who advised it.

A useful safeguard is to state, in the cost report, which assumptions each saving depends on. Surveyor Success describes "value erosion" as changes justified by budget targets rather than function analysis. A documented link between each option and the function it protects is the simplest defence.

Keeping quantities traceable through revisions

Value engineering produces several drawing issues in quick succession. The discipline that matters is traceability: for every quantity, you should be able to say which drawing it came from, which revision, how it was measured and who checked it. That is what lets you defend a saving to a client or a contractor months later.

A workable routine:

  1. Log each drawing issue and the date received.
  2. Re-measure only what has changed, and mark the affected bill items.
  3. Keep omitted and added quantities in separate, labelled schedules.
  4. Record rates and their source against each priced item.
  5. Have a second person check any item that drives a headline saving.

The same logic applies wherever quantity data supports a financial decision. A RICS rebuild cost assessment for a block of flats, for example, depends on sound quantity data in the same way a value engineering exercise does. If your quantities come from models, our guide to BIM quantity extraction covers how to check them, and the case for auditing every automated draft applies equally to any tool-generated figure.

Where QuantiFlow fits

QuantiFlow is in development. It reads construction drawings and produces a draft bill of quantities for a quantity surveyor to review and sign off. Judgement on what counts as value stays with you. You can see the plans on the QuantiFlow site.

Quantiflow

FAQ

Is value engineering the same as cost cutting?

No. RICS describes value engineering as a structured process that removes unnecessary cost to improve the ratio of benefit to cost. It does not cover reducing scope, omitting work items or lowering the specification below the client's required performance. Cost cutting is usually reactive, applied after a budget has been exceeded.

When should the quantity surveyor get involved?

As early as possible. RICS's commercial management standard says value engineering is best undertaken between project inception and detailed design. A 2020 academic study of value management workshops also finds that the QS should be introduced at the earliest opportunity so there is time to review costs and alternatives.

How do you price a value engineering option?

Quantify the change in scope, omitted and added, and apply rates for identical or similar work. Then consider the effect on preliminaries, risk allowances, design fees, overheads and profit. For dissimilar work, form a new rate and revisit economies of scale, as RICS's Valuing Change guidance sets out.

Why does late value engineering carry more risk?

RICS guidance shows the cost of change rises and its impact falls as a project progresses. Under NRM 2, poorly described information can also lead to variations and claims. Under a JCT contract with quantities, the employer holds the risk of quantity errors against the stated measurement rules.

Sources

This article is for general information only and is not professional, legal or commercial advice. Quantity surveying decisions should be taken by a qualified professional with reference to the specific project, drawings and contract in question. Content is produced with AI assistance and reviewed before publication. QuantiFlow Ltd accepts no liability for reliance on it.