A bill of quantities item number should do one job: identify one item, once, for the life of the project. Under NRM2 that means choosing the bill's breakdown structure first, then building a hierarchical code that rolls up from measured sub-component to element to bill to project, and never reusing a code once it has been issued.
This guide is for quantity surveyors, small builders and architects working to UK practice. It covers how the RICS codification framework works, a worked example, the order of items within a section, and how to handle additions, omissions and revisions without creating duplicates.
TL;DR
- Choose the breakdown first: elemental, work section or works package. The structure decides the bill sequence and what the numbers mean.
- NRM2 recommends a codification framework in which every component and item is uniquely identified, so information can be linked, retrieved and restructured without ambiguity.
- Keep the item code in its own column, separate from the description, because variations and queries refer back to it.
- Never recycle a code. Mark omitted items as omitted and give genuinely new items the next unused number in their parent group.
- Keep document revision numbering separate from item numbering.
Table of Contents
- Choose the breakdown structure before you number anything
- How the NRM2 codification framework is built
- A worked example: from project number to sub-component
- Numbering a work section bill
- The order of items inside each section
- Keep the code in its own column
- Numbering new, omitted and revised items
- A numbering routine for a small practice
- Where a draft BoQ tool can help
- FAQ
- Sources
Choose the breakdown structure before you number anything
Numbers only make sense inside a structure. NRM2 Appendix A sets out three principal breakdowns for a bill of quantities, and the NRM2 text on Appendix A.1 describes them as follows:
- Elemental: each NRM1 group element forms a separate bill section, subdivided into elements and sub-elements.
- Work section: the bill is divided into the work sections listed in NRM2 Part 3.
- Works package: packages defined by the client or the contractor.
The choice drives the bill sequence. An elemental bill, for example, runs through Preliminaries, Facilitating Works, Substructure, Superstructure, Internal Finishes, Fittings, Furnishings and Equipment, Services, External Works, Risks, Provisional Sums, Credits and Daywork, with each element or work section bill starting on a new sheet.
Which should a small practice pick? An elemental bill lines up with an elemental cost plan, so the client's budget and the tender return can be compared like for like. A work section bill groups similar products and components together, which many contractors find easier to price. If you are unsure which suits the job, our note on which bill of quantities format to use sets out the trade-offs. Whichever you choose, fix it before the first item is numbered. Changing the structure halfway through a bill means renumbering everything beneath it.
How the NRM2 codification framework is built
RICS NRM2 recommends a codification framework that uniquely identifies building components and items, so that information can be linked, retrieved, managed and restructured without ambiguity. In plain terms: one item, one code, and the code tells you where the item sits.
For an elemental bill, NRM2 identifies levels for project, bill, group element, element, sub-element and a user-defined component level. Because bill items are measured in greater detail than a cost plan, NRM2 adds a user-defined level for each measured sub-component. The numbering logic rolls up: sub-components into sub-elements, sub-elements into elements, elements into group elements and group elements into the project. The cost-planning end of the numbering is set out in NRM1.
The RICS NRM2 document describes the scheme as follows:
| Level | What it identifies | Who defines it |
|---|---|---|
| 0 | Project number | You |
| 1 | Cost plan number | You |
| 2 | Group element | Predefined by NRM1 |
| 4 | Sub-element | Predefined by NRM1 |
| 5 | Component | User-defined |
| 6 | Each sub-component measured under NRM2 | User-defined |
The scheme is numeric. NRM2 allows alphabetical codes too, but the same coding should be used for the cost plan and the bill so that every item can be traced back to the cost plan. If you cost-plan with one scheme and measure with another, you will spend tender week reconciling the two.
For the standard itself, the RICS NRM page lists the NRM2 download. If you want a fuller walk-through of the standard, see NRM2 explained.
A worked example: from project number to sub-component
The RICS document includes a clear example. Project DPB27, bill 3 (substructure), foundations, piled foundations, a pile cap, then the measured sub-components. The first code reads:

DPB27-3.1.1.2.1.1
Broken down:
| Part | Meaning |
|---|---|
| DPB27 | Project |
| 3 | Bill 3, substructure |
| 1 | Substructure group element |
| 1 | Foundations |
| 2 | Piled foundations |
| 1 | Pile cap |
| 1 | Sub-component: excavation |
The next sub-components under the same pile cap carry on from there. In the RICS example they are numbered .2 for disposal, .3 for concrete, .4 for reinforcement and .5 for formwork, giving DPB27-3.1.1.2.1.2 to DPB27-3.1.1.2.1.5.
Two things are worth copying from this. First, the code is built from the structure, so anyone reading it can place the item without opening the bill. Second, the last digit is the only thing that changes between items of the same component. That makes gaps and duplicates easy to spot.
Under NRM2 each item should carry a unique code, an identifying description and a firm quantity, all presented within the chosen breakdown. RICS defines the bill as a coordinated list of items with identifying descriptions and quantities, used to obtain tenders and then to value work executed and varied work. That second use is why numbering matters: the code is what you will be quoting in valuations and variations months later.
Numbering a work section bill
If you take the work section route, the sections themselves are numbered. NRM2 work sections run from 1 to 41, replacing the A to Y lettering used under SMM7. A small practice moving across from older habits should note that a code such as D20 belongs to the old lettered scheme, while a number-led code such as 4.1.1 belongs to the numbered one. Mixing the two in a single bill is a common source of confusion for contractors pricing it.
A simple, workable pattern for a work section bill is:
- Work section number (for example, 11 for the section you are measuring).
- Work group or subdivision within the section.
- Item number within that subdivision.
So the third item in the second subdivision of work section 11 reads 11.2.3. Keep the same number of levels throughout the bill. If some items run to three levels and others to five, filters and roll-ups stop working.
Preambles go in the relevant element or work section, prime cost sums are incorporated in the item descriptions, and provisional sums are listed in a separate bill, as set out in NRM2 Appendix A.3. Construction risks transferred to the contractor are set out in a schedule of construction risks. Each of these has its place in the numbering sequence, so decide where they sit before you start.
The order of items inside each section
Numbering and ordering go together. Within each element or work section subdivision, NRM2 Appendix A.3 sets the order of measured items:
- Cubic items
- Square items
- Linear items
- Enumerated items
- Itemised items
Labour-only items precede labour-and-material items, and items within each subdivision are placed in order of value, least expensive first. Number in that order, so the sequence of codes follows the sequence on the page. When numbering and page order disagree, readers assume something has been moved or deleted.
The same appendix is the basis for the order of the wider bill. If you are working through the measurement rules themselves, our guide to NRM2 takeoff rules covers how to keep measurement auditable.
Keep the code in its own column
A code buried inside a description is a code that cannot be filtered. Every item needs a reference, a description, a quantity and a unit, with columns for the contractor's rate and amount. Give the reference its own column.
There are practical reasons for this:
- Variation pricing refers to the bill by item code.
- Drawing reconciliation and post-tender clarifications do the same.
- Sorting, grouping and rolling up totals by element only work if section, group and item are separate fields.
If you export to Excel, set the code column as text. Spreadsheets will happily turn 3.1.10 into 3.1.1 or a date, and nobody notices until the totals disagree.
It also helps to settle the other fields that sit next to the code. Our piece on six fields to standardise BoQ items lists what to record alongside each reference so lines stay comparable from one project to the next.
Numbering new, omitted and revised items
This is where most numbering schemes break. Drawings change, items are added after the first issue, and someone renumbers the bill to tidy it up. Then a contractor's priced copy no longer matches yours.
A workable convention, in line with the RICS aim of unique identification, is:
- New item: give it the next unused number in its parent group. If the last pile cap item was .5, the new one is .6, even if it logically belongs between .3 and .4. Describe where it belongs in the description or a cross-reference.
- Omitted item: leave its number unused. Keep the line, mark it omitted, and never assign that number to something else.
- Revised item, same work: keep the same code. A change in quantity or a clarified description is recorded in the bill's revision log, not in a new number.
- Revised item, materially different work: omit the old line and issue a new, unused code for the new one.
This is practice rather than a rule printed in NRM2, so write your convention into the bill's preliminaries or cover note and apply it consistently.
Keep document revision numbering apart from item numbering. Document versions such as v1.0, v1.1 and v2.0 track changes, while status labels such as draft, final and superseded show where a record stands, as the University of Sussex records management guidance explains. Applied here, "Revision C" belongs to the bill; "3.1.1.2.1.4" belongs to the item. Neither should leak into the other.
If you also need each line tied to the drawing it was measured from, see linking each BoQ line to its drawing revision.
A numbering routine for a small practice
For a typical SME job, the following sequence works:
- Pick the breakdown (elemental, work section or works package) and record the choice.
- Fix the project code and, for elemental bills, align the upper levels with the cost plan.
- Set the number of levels and keep it the same across the bill.
- Allocate bill numbers in the order the bill will be presented, with provisional sums, risks, credits and daywork placed deliberately.
- Number items in NRM2 order within each subdivision.
- Leave the reference in its own column and format it as text.
- Write the revision convention into the bill: how new, omitted and changed items are handled.
- Check before issue: no duplicate codes, no gaps without a note, and the same codes used in the cost plan.
For a deeper look at how codes are constructed, the NRM2 item coding guide goes through further patterns.
Where a draft BoQ tool can help
Numbering is mechanical but easy to get wrong when a bill is long and the drawings keep changing. QuantiFlow is in development: it reads construction drawings and produces a draft bill of quantities for a quantity surveyor to review and sign off. The numbering convention, the structure and the final judgement stay with you.
You can find out more on the QuantiFlow site.
FAQ
What is the correct format for a BoQ item number under NRM2?
NRM2 recommends a hierarchical numeric code built from the breakdown structure. The RICS example, DPB27-3.1.1.2.1.1, runs from project to bill, element, sub-element, component and measured sub-component. Alphabetical codes are allowed, but they should match the cost plan.
Can I use SMM7 letters such as D20 in an NRM2 bill?
NRM2 replaced the SMM7 A to Y work section lettering with numbered work sections 1 to 41. For a new NRM2 bill, use the numbered scheme throughout. Mixing letters and numbers makes the bill harder to price and to reconcile.
What should I do with an item that is no longer needed?
Do not delete its number and do not reuse it. Keep the line, mark it as omitted, and record the change in the revision log. That way anyone holding an earlier issue can still match their lines to yours.
Should the item code be part of the description?
No. Give it a separate column. Variations, valuations and clarifications all refer to the item by code, and a separate field lets you filter, group and roll up totals reliably.
Do I need the same numbering for the cost plan and the bill?
Yes, wherever you can. RICS advises using the same coding for both so each bill item references back to the cost plan, which makes comparing the budget with tender returns far quicker.
Sources
- RICS NRM 2, October 2022 update
- RICS NRM 2, October 2022 edition
- RICS NRM 2, first edition (2012)
- RICS NRM: New Rules of Measurement
- NRM 2 Appendix A, detailed measurement for building works
- University of Sussex, record naming and version control
Recommended
- NRM2 Item Coding: How Bill of Quantities Codes Are Built
- 6 Fields to Standardize BoQ Items for UK QSs with NRM2 and Uniclass
- NRM2 takeoff rules to make BoQs audit ready for UK quantity surveyors
- NRM2 explained: the RICS standard for measuring building works
This article is for general information only and is not professional, legal or commercial advice. Quantity surveying decisions should be taken by a qualified professional with reference to the specific project, drawings and contract in question. Content is produced with AI assistance and reviewed before publication. QuantiFlow Ltd accepts no liability for reliance on it.